Renewable Energy

Solar + Battery Project at the Regional Intermodal Transportation Center (RITC)

We’re partnering with Hollywood Burbank Airport and Baker Electric to build a 2 megawatt solar system with battery storage. The project will provide enough power for about 585 homes.

2 Megawatt Solar System

2 Megawatt/8 Megawatt Hour Lithium-ion Battery Storage System
Zero-Carbon Power Source
May 2026 Estimated Completion
Can Power 585 Homes

Construction Started in July 2025

Construction on the RITC Solar + Battery Project officially began in July 2025, marking a major milestone in Burbank’s transition to a cleaner, more sustainable future. Over the coming months, crews will install more than 4,000 solar panels and an advanced battery storage system. The construction phase is anticipated to be completed by May 2026, and will begin delivering zero-carbon power to the Burbank community.

How the Solar + Battery Project Works

The Benefits for Burbank

 

  Backup Power

 

Provides enough backup power for 585 homes, or ~30 offices, or ~7 schools

 

  Grid Support

 

Reduces peak load stress on utility infrastructure, helping to prevent power outages.

  Cost Savings

 

 

 

Allows BWP to draw from stored electricity when additional power is needed for Burbank instead of buying additional power with fluctuating prices.

  Clean Energy

 

 

 

The more renewables that are available, the more Burbank can reduce the use of fossil fuels.

  Resilience

 

 

 

Helps keep critical services running and recover quickly during emergencies such as power outages, wildfires, and heatwaves.

FAQs for the RITC Solar + Battery Project

The RITC Solar + Battery Project is Burbank’s largest solar energy installation, combining a 2-megawatt solar system with an 8-megawatt-hour lithium-ion battery storage system to deliver zero-carbon power to the community.
The RITC Solar + Battery Project supports Burbank’s goal of achieving 100% zero-carbon energy by 2040, while also enhancing grid reliability and long-term sustainability for the city.
The project is located at the Regional Intermodal Transportation Center (RITC) at Hollywood Burbank Airport. The location is an ideal site for this initiative due to its available space and strong solar exposure.
Solar energy needs space. In dense areas like Burbank, finding the optimal sun exposure for large solar installations can be a major challenge. The RITC has the space and sun exposure needed for a large solar installation, making it an ideal location for the Solar + Battery Project.
Construction began in July 2025 and is expected to be completed by May 2026.
The system is designed to generate 2 megawatts, which is enough energy to power approximately 585 homes.
Battery storage enables the solar system to store excess energy for use during peak times or when sunlight is unavailable, thereby improving reliability and efficiency.
The project is a collaboration between BWP, Hollywood Burbank Airport, the Burbank-Glendale-Pasadena Airport Authority, and Baker Electric.
You can explore BWP’s Integrated Resource Plan and clean energy goals on our website here: 2024 IRP.